MONTHLY CONSTRUCTION PROGRESS REPORT
LOS ANGELES TRADE TECH COLLEGE - June 2005
Return to LATTC Home Page
List of abbreviations and terms used on these pages.
1.0     EXECUTIVE SUMMARY

•  Pending approval of the CPM contract for the next 3-year phase, the present ACG & AVA contract has been extended through the end of July 2005.

•  On June 15, 2005 the College President and CAJA (EIR consultant) presented the 30-Year EIR Master Plan to the BOT.   EIR Certification and Adoption of the 30-Year EIR Master Plan will be placed on the July 13, 2005 BOT agenda for approval by the BOT, culminating the EIR approval process.

•  The Inspector of Record completed the Final Inspection of the Auto Metal Package 2 project site on June 9, 2005 and Notice of Final Completion was issued to the IOR on June 19, 2005.   The CPM has transmitted the Final Completion Certificate and final Change Order to the architect for signatures.

•  The DSA, Constructability and ACG & AVA review comments for South Campus have been compiled into an Excel database and the comment resolution process has started.

•  The G & J building 100% CD package was submitted to DSA for plan check review on June 20, 2005.

•  The DSA review comments for F Ramp have been compiled into an Excel database and transmitted to Kishimoto Architects for review and resolution.   Fire Life Safety and Accessibility plans are still being reviewed by DSA.

•  Substantial Completion of the Construction Technology Yard was signed off on June 6, 2005. Completion of final punch list items are currently in progress.

•  CPM technical review comments (electrical and mechanical) on the Olive Street Parking Structure 100% DD plans were compiled and transmitted to ARB on June 8, 2005 for review and resolution.

Project Title Status

Auto Metal Building- HVAC Upgrade and Modernization-

IN CONSTRUCTION

Pkg 1:   LACCD payment for final Change Order is pending.

Pkg 2: All substantial punch list work completed. Final Completion Certificate prepared and signed by the Contractor, Inspector of Record and Architect of Record; and will be submitted to BOT on August 3, 2005 for Final Completion acceptance.

Pkg 3: IOR inspected outstanding punch list item and acknowledged that it was complete.

Amount Encumbered-$ 5.93 M

Next Milestone date – Submit final Notice of Completion Certificate for BOT acceptance on August 3, 2005.

Construction Technology Yard-

IN CONSTRUCTION

Project Substantially Complete on June 6, 2005. Punch list item correction is currently in progress.

Amount Encumbered-$ 0.48 M

Next Milestone date - Final completion including punch list items is scheduled for July 2005.

F-Ramp-

DESIGN PHASE

The 100% CD package was submitted for DSA review on March 28, 2005.

Amount Encumbered - $ 0.32 M

Next Milestone date - DSA review is scheduled for completion by August 2005.   Constructability review concurrent with DSA review.

Gymnasium-

DESIGN PHASE

The 100% CD package was submitted to DSA on June 20, 2005 inclusive of drawings, specifications, Geo-tech report, and Title 24 calculations.  

Amount Encumbered - $ 1.1 M

Next Milestone date

DSA will provide the Application number and File ID number along with preliminary review schedule dates and inspector requirement.   

South Campus-

Demolition,

North & South Building, Subterranean Parking & Athletic Field,

On/Off Site Improvements- DESIGN PHASE

CPM completed compiling DSA red line comments for Fire Life Safety, Accessibility and Structural review and the package has been returned to the architect. CSS and ACG & AVA review comments have also been returned to the architect.

Amount Encumbered - $ 7.93 M

Next Milestone date - Architect to incorporate all review comments into CD and resubmit for back check by CPM, DMJM/JGM, and DSA.

Olive Street Parking Garage

The CPM completed the technical review of DD packages for design cost adjustments on June 9, 2005. The CPM has requested ARB to submit the schedule of milestone activities by the end of June 2005.  

Amount Encumbered- $ 0.32 M

Next Milestone date - Completion of schedule and 50% CD submittal.

Auto Metal Building- Solar PV Panel

DESIGN PHASE

The project is on hold, pending resolution of Siemens contract by LACCD legal dept.

Amount Encumbered - $ 0.077 M

Next Milestone date – No new activity.

Emergency Lighting, Fire Alarm, and Security Systems - Electrical Site Distribution

DESIGN PHASE

M-E Engineers submitted the revised 100% CD package for review and comment on June 21, 2005 and attended a technical review meeting with LATTC Facilities to finalize construction notes for the drawings and specification.  

Amount Encumbered - $ 0.044 M

Next Milestone date – Completion of 100% CD submittal.

Cost Status:

Following is a cost status summary:

Encumbered Amount: $ 40.33 Million

Prop A & AA Bond Fund Amount including

Interest & State Contributions: $ 239.79 Million

% Encumbered:   16.82%

Details of the cost status are presented under Section 4.0

Schedule Status:

CONSTRUCTION SCHEDULE COMPLETION

Auto Metal Building (Phase II):

Pkg. 2:   Substantial Completion

punch list items – 99%

Construction Tech Yard:

Underground Utilities - 100%

Modular Facility  – 100%

Fence Installation & Painting – 100%

Landscape & Irrigation – 100%

Electrical Upgrades and Misc. Work – Liberal Arts Building

Installation of J-Box for 3 Classrooms – 10%

Installation of New Panel/Conduits – 0%

Installation of New Cables – 0%

Details of the Schedule status are presented under Section 5.0

Bid Information:

Project

Bid Ad

Pre Bid Conference

Bid Open

BOT Approval

Const. Start

*CDC

Aug 2005

Sept 2005

Oct 2005

Nov 2005

Dec 2005

*F Ramp

Sep 2005

Sep 2005

Oct 2005

Nov 2005

Dec 2005

*Electrical    Upgrade –Bldg. A

Mar 2005

Mar 2005

April 2005

May 2005

June 2005

*IT – CDC

June 2005

July 2005

July 2005

Aug 2005

Sep 2005

*Power Distribution

July 2005

Aug 2005

Aug 2005

Sep 2005

Oct 2005

Utility Tunnel Repair – Bldg A

July 2005

Aug 2005

Aug 2005

Sep 2005

Sep 2005

* Projected Bid dates for next construction project


4.0 BUDGET STATUS REPORT
Available Funds
Proposition "A" Bond Fund $138,000,000  
Proposition "AA" Bond Fund $89,600,000
Interest Fund Incorporated to Rebaseline Projects $5,518,593
Funds under Proposition "A" & "AA" Bond $233,118,593
State Contributions $5,554,071
Interest Earned (As of March 31, 2005) - Uncommitted $1,122,273
Total Funds available as of June 30, 2005 $239,794,937
Projected Cost at Completion of Present Prioritized Projects $238,834,177
General Contingency $960,760
BUDGET $239,794,937
BUDGET FOR HARD COSTS 76.11% $182,499,830
Budget for Hard Costs $181,539,069  
General Contingency $960,760
BUDGET FOR SOFT COSTS 23.83% $57,133,595
COMMITTED TO DATE 16.82% $40,331,962
HARD COSTS 8.00% $19,182,281
Hard Construction Costs $8,725,889
Land Acquisitions $10,456,392
SOFT COSTS 8.82% $21,149,681
EXPENDED TO DATE 13.39% $32,118,968
HARD COSTS 6.77% $16,239,716
Hard Construction Costs $5,800,277
Land Acquisitions $10,439,439
SOFT COSTS 6.62% $15,872,806