1.0     EXECUTIVE SUMMARY

•  ACG & AVA was a Gold Sponsor in support of the LATTC Associated Students Organization (ASO). The ASO inaugurated Dr. Daniel A. Castro as the 11 th President of the College at a dinner reception held on May 26, 2005 to recognize outstanding Students of LATTC and celebrate the Students' inauguration of Dr. Castro.   The LATTC CPM team attended the gala event.

•  On 5/15/05 the 45-day CEQA required public review period for the 30-Year EIR ended with zero comments from the public.   The Final 30-Year EIR is scheduled to be completed and ready for BOT distribution on May 31, 2005.

•  On May 24, 2005 the project Inspector of Record and DSA Engineer walked the Auto Metal building project site and developed a list totaling three outstanding items.   Scorpio provided Owner training for Start-Up and Cooling Tower operation on May 20, 2005.   Punchlist and Warranty items are being finalized by the CPM and Contractor.

•  On May 25, 2005 the CPM completed data entry of the DSA comments in to a spread sheet for review and resolution of the South Campus Accessibility and Fire Life Safety plans.   The South Campus Structural plans and Specification were received by the CPM on May 26, 2005.  

•  The F Ramp 100% plans are still in DSA review.   Kishimoto Architects (KAI) is responding to CSS constructability review comments.   LATTC Facilities, KAI and TRC EASI have been coordinating to discuss security and equipment layout for the F Ramp.

•  On May 19, 2005, ARB submitted the 100% DD package for review and comment.   An Olive Street Parking Structure pre-Construction meeting was held with ARB on May 19, 2005 and Notice to Proceed was issued on May 27, 2005.

•  Pugh Scarpa Kodama submitted the building G & J 100% DSA submittal to the CPM on May 23, 2005.   The CPM Estimate was completed on May 27, 2005. The 100% G & J plans are tentatively scheduled for delivery to DSA by June 6, 2005.

Project Title

Status

Auto Metal Building- HVAC Upgrade and Modernization-

IN CONSTRUCTION

Pkg 1:   LACCD payment for final Change Order is pending.

Pkg 2: Substantial punch list completion continues.   Replaced defective connectors for fiber optic cables and system retested. Retest report forwarded to LATTC Facilities for approval. Change Order for replacement of telephone equipment/systems is processed. Final completion walk thru held on 5/24/05.

Pkg 3: Work on the punch list items for Package 3 is still pending by LACCD.

Amount Encumbered-$ 5.90 M

Next Milestone date – Substantial punch list items pending, tentatively scheduled for late June.

Construction Technology Yard-

IN CONSTRUCTION

An RFC for Change Order # 1 for rain delays and the completion of the Modular Facility is scheduled for BOT approval June 2005.

Amount Encumbered-$ 0.47 M

Next Milestone date - Substantial completion is scheduled for 6/3/05.

F-Ramp-

DESIGN PHASE

The 100% CD package was submitted for DSA review on 3/28/05.

Amount Encumbered - $ 0.31 M

Next Milestone date - DSA Review is scheduled for completion by August 2005. Constructability review concurrent with DSA review.

Gymnasium -

DESIGN PHASE

The 100 % CD package will be submitted to DSA by the end of May 2005, and reconciliation of the three Estimates.

Amount Encumbered - $ 1.1 M

Next Milestone date 100% CD

package scheduled for submittal to DSA by 5/31 /05.

South Campus- Demolition,

North & South Building, Subterranean Parking & Athletic Field,

On/Off Site Improvements- DESIGN PHASE

Fire Life Safety and Accessibility review completed by DSA for the 100% CD documents and sent back to the Architect. MDA JF delivered the DSA comments on the Structural plans and Specification on 5/26/05. The CPM began data entering DSA comments in to a database. Constructability review by consultant CSS completed and review comments have been submitted.

Amount Encumbered - $ 7.89 M

Next Milestone date - CPM to review the Constructability comments from CSS and forward them to MDA JF by end of May 2005.

CPM is also incorporating red line comments from DSA in to spread sheet and will return red line drawings to MDA JF by the end May 2005.

Olive Street Parking Garage

Pre-Construction meeting held with ARB on 5/19/05.

Amount Encumbered- $ 0.29 M

Next Milestone date - The NTP was issued on 5/27/05.

Auto Metal Building- Solar PV Panel

DESIGN PHASE

The CPM has assisted Siemens with assembling the electrical billing history of LATTC for the 2004/2005 year for calculation of pay-back performance.

Amount Encumbered - $ 0.089 M

Next Milestone date - Approval of the Solar Power Incentive Program form.

Cost Status:

Following is a cost status summary:

Encumbered Amount: $ 40.20 Million

Prop A & AA Bond Fund Amount including

Interest & State Contributions: $ 239.79 Million

% Encumbered:   16.76%

Details of the cost status are presented under Section 4.0

Schedule Status:

CONSTRUCTION SCHEDULE COMPLETION

Auto Metal Building (Phase II):

Pkg. 2:   Substantial Completion

punch list items – 99%

Construction Tech Yard:

Underground Utilities - 100%

Modular Facility  – 100%

Fence Installation & Painting – 100%

Landscape & Irrigation – 100%

Details of the Schedule status are presented under Section 5.0

Bid Information:

Project

Bid

Ad

Pre Bid Conference

Bids Due

BOT Approval

Const.

Start

*CDC

May 2005

June 2005

July 2005

Aug 2005

Sep   2005

*F Ramp

Sep 2005

Sep   2005

Oct   2005

Nov 2005

Dec   2005

*Electrical    Upgrade –Bldg. A

Mar 2005

Mar  2005

April 2005

May 2005

June 2005

*IT – CDC

June 2005

July 2005

July 2005

Aug 2005

Sep 2005

*Power Distribution

July 2005

Aug 2005

Aug 2005

Sep 2005

Oct 2005

* Projected Bid dates for next construction project


Budget Status Report
Available Funds
Proposition "A" Bond Fund $138,000,000  
Proposition "AA" Bond Fund $89,600,000
Interest Fund Incorporated to Rebaseline Projects $5,518,593
Funds under Proposition "A" & "AA" Bond $233,118,593
State Contributions - See Note #1 $5,554,071
Interest Earned (As of March 31, 2005) - Uncommitted - See Note #2 $1,122,273
Total Funds available as of May 31, 2005 $239,794,937
Projected Cost at Completion of Present Prioritized Projects $238,929,895
General Contingency $865,042
BUDGET $239,794,937

BUDGET FOR HARD COST

76.07% $182,404,112

Budget for Hard Costs

$181,539,069  

General Contingency

$865,042

BUDGET FOR SOFT COSTS

23.83% $57,133,595
COMMITTED TO DATE 16.76% $40,200,081

HARD COSTS

7.99% $19,175,619

Hard Construction Costs

$8,719,227

Land Acquisitions

$10,456,392

SOFT COSTS

8.77% $21,024,462
EXPENDED TO DATE 13.00% $31,174,737

HARD COSTS

6.76% $16,202,436

Hard Construction Costs

$5,762,997

Land Acquisitions

$10,439,439

SOFT COSTS

6.24% $14,972,301
Notes
1 The revised state contribution for the Auto/Metal Building project- HVAC Upgrade and Hazardous Substance Removal, as based on the report presented by Bruce Rosky of LACCD on April 29, 2005, is reflected in this report.
2 Based from DMJM/JGM Financial Report, the total earned interest as of March 31, 2005 is $6,640,866.32, the sum of $6,395,839.53 and $245,026.79 for Prop "A" and "AA" respectively. Of the Prop "A" interest earned, $5,518,593 had been incorporated with the rebaseline budget and the remaining uncommitted interest earned of $1,122,273.32 (6,640,866.32 - $5,518,593.00) will be recommended to the LATTC Management for funding unforeseen project scope changes and market condition.
3 Since the contract amounts for all District-wide On-Call Inspection and Testing Services, under Ledger 07T.6795.05, allocated for each Campus are not well established, only amounts stipulated in Task Orders under each respective project are reflected in this cost report.