MONTHLY CONSTRUCTION PROGRESS REPORT
LOS ANGELES TRADE TECH COLLEGE - Feburary 2005
Return to LATTC Home Page
List of abbreviations and terms used on these pages.

EXECUTIVE SUMMARY

•  The second floor classrooms of the Auto Metal “F” Building are now being used by the students and teachers.   Except for a few punch list items the construction is essentially complete.   A ribbon cutting ceremony was held on 2/24/05 and the construction of the 2 nd floor was officially accepted. This is the first construction project at LATTC and had a mix of Bond & Non-Bond project sections.

•  The construction for the Construction Technology Yard (CTY) Project has been delayed for 21 days due to heavy rains.   This is the second construction project at LATTC being managed by ACG/AVA CPM.

•  The 100% CD document preparation is on schedule for the “F” Ramp Project and is planned for DSA Submittal early March 2005.

•  For the Olive Street Parking Structure Design Build Project all activities including “Best and Final” Offer is on schedule and board action for contractor selection is scheduled for March 2005.

•  Gymnasium Building “G” and “J” Project 100% CD Submittal has been delayed until 3/11/05 to incorporate all review comment resolutions prior to DSA Submittal.   It is expected that the 100% CD will be received during the 2nd week of March.

•  The CPM move to the LRC Basement is planned for the first week of March 2005.   The construction progress is ahead of schedule.

Project Title

Status

Auto Metal Building-
HVAC Upgrade and Modernization-

IN CONSTRUCTION

Pkg 1:   LACCD Payment for final Change Order pending.

Pkg 2: Substantial completion given on 2/4/05.   Substantial Punch list completion continued through February 2005.

Pkg 3: Work on the punch list items for Package 3 are still pending.

Amount Encumbered -$ 5.80 M

Next Milestone date - Substantial punch list items scheduled to be complete by early March 2005.

Construction Technology Yard-

IN CONSTRUCTION

Foundation for the Modular Facility is complete.   Rain hampered the progress of the project by 21 days.

Amount Encumbered -$ 0.47 M

Next Milestone date- S ubstantial completion scheduled for 03/05/05.

F Ramp-

DESIGN PHASE

The CPM coordinated a meeting with DMJM/JGM estimators and the Architect to finalize budget basis of DSA fee schedule.

Amount Encumbered - $ 0.27 M

Next Milestone date - 100% documents scheduled to be submitted to DSA by early March 2005 after the DMJM's final construction budget is determined by APM.

Gymnasium -

DESIGN PHASE

The 100% CD Submittal has been delayed by two weeks .   A coordination meeting with LATTC Facilities is scheduled on 3/3/05 to confirm that all revisions are incorporated on the final drawings.

Amount Encumbered - $ 1.1 M

Next Milestone date - The completion of 100%CD package is scheduled by 3/11/05

South Campus-

Demolition, North & South Building, Subterranean Parking & Athletic Field, On/Off Site Improvements-

DESIGN PHASE

100% CD Documents still being reviewed by DSA.

NTP for Constructability review was given on 2/28/05 to CSS>   Expected completion of review is 90 days from NTP.

Amount Encumbered -$7.76 M

Next Milestone date - CPM to meet with CSS on 3/10/05 to discuss LEED™ scope of work relative to Constructability review.

Olive Street Parking Garage

The CPM assisted DMJM/JGM with the “Best and Final Offer” process in terms of issuing Addendum 8 & 9

Amount Encumbered- $ 0.28 M

Next Milestone date - Intent to award for the D/B project with scheduled BOT approval by 3/23/05

Auto Metal Building -
Solar PV Panel

DESIGN PHASE

The final version of contract documents is still under review by LACCD/Legal Department.   

Amount Encumbered -$ 0.89 M

Next Milestone date - Design Phase of the project will commence when LACCD/Legal approves the final version of the contract documents.    Date to be determined.

Cost Status:

Following is a cost status summary:

  • Encumbered Amount: $ 39.85 Million
  • Prop A & AA Bond Fund Amount: $ 235.25 Million
  • % Encumbered: 16.94%

Details of the cost status are presented under Section 4.0

Schedule Status:

CONSTRUCTION SCHEDULE COMPLETION

Auto Metal Building (Phase II):

Pkg 2:   Substantial punch list items – 98%

Construction Tech Yard:

Underground Utilities - 100%

Modular Facility Foundation – 100%

Details of the Schedule status are presented under Section 5.0

Bid Information:

Project

Bid Ad

Pre Bid Conference

Bids Due

BOT Approval

Const. Start

CDC

NA

NA

NA

NA

NA

F Ramp*

Jun 2005 *

-

Aug 2005 *

-

Oct 2005 *

* Projected Bid dates for next construction project